Appeal Decision 22 -
Certificate of Lawful Development.
The
following appeal summary has been written by Steve
Speed, and is available on his website
www.planningjungle.com
28 August 2009 – 25 Malta Road,
London, E10 7JT
Planning
Inspectorate Reference: APP/U5930/X/09/2094008
London
Borough of Waltham Forest Reference:
2008/1760/CLP
Summary of Case (appeal
dismissed):
·
The
property is a two-storey mid-terrace house, with an original
two-storey rear projection. The application was for an
existing roof extension (begun after 1 October 2008) over the
original two-storey rear projection.
The Inspector noted that the roof extension exceeds the height
of the ridge-line of the “original rear section”, and concluded
that it is therefore contrary to Class B, part B.1(a), which
states that “development is not permitted by Class B if … any
part of the dwellinghouse would, as a result of the works,
exceed the height of the highest part of the existing
roof”. This would
appear to suggest that where a property has an original rear
projection, a roof extension on top of this rear projection can
notbe higher than the ridge-line of the latter (as opposed to
the view that it can not be higher than the main
ridge-line).
However, from a conversation with the Council, it appears that
in this case the roof extension did actually exceed the height
of the main ridge-line, and therefore it appears that the above
suggestion should not be applied. Furthermore, it would appear
that there is caselaw (Hammersmith & Fulham L.B. v S.O.S.
30/11/1993) that confirms that the phrase "height of the
highest part of the existing roof" refers to the dwelling as a
whole (i.e. the main ridge-line) and not the
particular part of the roof where works were to be carried out.
[Source: DCP Online, section 4.3447].
The Inspector also examined the issue that the roof extension
has not been set-back from the eaves of the original roof,
noting that Class B, part B.2 (a) states that “the edge of the
enlargement closest to the eaves of the original roof shall, so
far as practicable, be not less than 20 centimetres from the
eaves of the original roof”. The applicant had claimed
that in this case this set-back was not practicable, as such an
inset could only be achieved by introducing a new structural
beam to support the wall, floor and roof of the extension;
which would have meant both additional cost and delay before
the works could have been carried out. The Inspector disagreed with
this argument. He
stated that in most situations it will be necessary to
introduce one or more structural beams in order to form a roof
enlargement with an inset from the eaves of the original roof
of not less than 20cm, that the provision of such beams will
inevitably involve additional cost, and that there is no
evidence before him to demonstrate that in this case those
works would have been unacceptably expensive. In addition, the Inspector
stated that simply because the scheme might have been a delayed
as a result of this set-back is not a sufficient reason to find
that the set-back is not practicable.
Main Conclusion:
·
The fact that the 20cm set-back of a roof extension would
result in additional cost or delay is not sufficient in itself
to justify that such a set-back would not be
“practicable”.
Link to
case on Planning Inspectorate website:
http://www.pcs.planningportal.gov.uk/pcsportal/ViewCase.asp?casename=APP/U5930/X/09/2094008&caseaddress=COO.2036.300.8.991689
Download
documents and diagrams of
useful
Permitted
Development information

|